4. VERIFICATION
4.1 Classification of inspections. The inspection requirements specified herein are
classified as follows:
a. First article inspection (see 4.3).
b. Conformance inspection (see 4.5).
1. Acceptance tests (see 4.5.3.1).
2. Control tests (see 4.5.3.2).
3. Comparison tests (see 4.5.3.3).
4.2 Materials. The contractor records shall be reviewed to determine conformance with
3.4 through 3.4.3.
4.2.1 Interchangeable repair/spare parts. The repair/spare parts specified (see 3.5.12)
shall be inspected for conformance to the requirements of their respective drawings contained in
the M149A2 trailer technical data package, Drawing 8750052.
4.3 First article inspection. First article inspections are categorized as preproduction
inspection or initial production inspection. Approval of the first article sample by the
Government shall not relieve the contractor of the obligation to supply trailers that are fully
representative of those inspected as a first article sample. Any changes or deviation of the
production units from the first article sample shall be subject to the approval of the contracting
officer.
4.3.1 Preproduction inspection. When specified (see 6.2), the preproduction sample
shall consist of one trailer. Preproduction inspection shall consist of examinations as specified in
table IV and tests specified in table III.
4.3.2 Initial production inspection. Unless otherwise specified (see 6.2 and 6.3.1) on
beginning production, three vehicles shall undergo, and shall pass, initial production inspection.
One vehicle shall undergo first production vehicle inspection, and the second and third vehicles
will be subjected to initial production test.
4.3.3 First article inspection failure. Failure of any first article sample to pass specified
examinations or tests shall be cause for refusal to grant first article approval until corrective
action by the contractor has been approved by the Government.
4.4 First production vehicle inspection.
4.4.1 In-process examination. During fabrication of the first production vehicle, an in-
process examination will be conducted by representatives of TACOM Product Assurance
Directorate to evaluate conformance of materials and workmanship to specified requirements.
Examination will be made at the contractor's facility prior to application of primer and paint.